- 1
Take off the 4 braces locking the compressor spring
- 2Make sure the unit is leveled and stable
- 3
Make sure the main switch is set to OFF
- 4Connect all wiring (certified electrician only)
- 5
Set the mode switch to zero (0)
- 6
Set the main switch to ON
- 7
Wait two hours, then set the mode switch to LOCAL
- 8
Let the unit run for 2 hours before moving on to the operation stage