Follow these steps to ensure smooth operation and maximize your DryGair’s longevity

Get Started Right: Watch the Initial Operation Checklist Video

  • 1

    Take off the 4 braces locking the compressor spring

  • 2
    Make sure the unit is leveled and stable
  • 3

    Make sure the main switch is set to OFF

  • 4
    Connect all wiring (certified electrician only)
  • 5

    Set the mode switch to zero (0)

  • 6

    Set the main switch to ON

  • 7

    Wait two hours, then set the mode switch to LOCAL

  • 8

    Let the unit run for 2 hours before moving on to the operation stage